That Project uses the
following formula, called the scheduling formula, to calculate a
task’s work value:
Work = Duration × Assignment Units
where assignment units are normally expressed as a percentage.
Remember also that a task has work when it has at least one work
resource (people or equipment) assigned to it. Each value in the
scheduling formula corresponds to a task type. A task type determines
which of the three scheduling formula values remains fixed if the
other two values change.
The default task type is fixed units: If you change a task’s
duration, Project will recalculate work. Likewise, if you change a
task’s work, Project will recalculate the duration. In either case,
the units value is not affected.
The two other task types are fixed duration and fixed work. For
these task types, Project uses a timephased field called peak units
when responding to schedule changes.
For a fixed-work task:
-
You can change the assignment units value and Project will
recalculate the duration. -
You can change the duration value and Project will
recalculate peak units per time period. The assignment units value
is not affected.
Note
You cannot turn off effort-driven scheduling for a fixed-work
task.
For a fixed-duration task:
-
You can change the assignment units value and Project will
recalculate work. -
You can change the work value and Project will recalculate
peak units per time period. The assignment units value is not
affected.
Project also keeps track of the highest peak units value per
assignment. This value is stored in the Peak field, which you’ll work
with in the sidebar.
Which is the right task type to apply to each of your tasks? It
depends on how you want Project to schedule that task. The following
table summarizes the effects of changing any value for any task type.
You read it like a multiplication table.
Note
You cannot change the task type of a manually scheduled task,
and the effect of the task type on the scheduling of a task as
described here applies only to automatically scheduled tasks.
To view the task type of the selected task, on the Task tab, in
the Properties group, click Information. Then, in the Task Information
dialog box, click the Advanced tab. You can also view the task type in
the Task Form. (When in the Gantt Chart view, you can display
the Task Form by clicking Details on the View tab, in
the Split View group.) You can change a task type at any time. Note
that characterizing a task type as fixed does not mean that its
duration, assignment units, or work values are unchangeable. You can
change any value for any task type.
In this exercise, you change a task type and some scheduling
formula values.
-
On the View tab, in the
Task Views group, click
Task Usage.
The Task Usage view appears. -
In the Task Name column,
select the name of task 8, Copyedit. -
On the Task tab, in the
Editing group, click Scroll to Task.
Tip
To select a task quickly, even a task you can’t see in the
current view, press Ctrl+G and in the ID field of the Go To
dialog box, enter a task number, and then click OK.
Project displays the details for task 8,
Copyedit, and its assignment.
The Task Usage view groups the assigned resources below each
task and shows you, among other things, each task’s duration and
work—two of the three variables of the scheduling formula. -
If necessary, drag the vertical divider bar to the right so
that the Finish column is
visible.
Next, you’ll add two columns to the Task Usage view so that
you can see the assignment units (the third variable of the
scheduling formula) and the peak values. You don’t need to modify
this view every time you want to use it, but for our purposes
here, this is a good way to illustrate the effect of changing task
types and scheduling formula values. -
Click the Start column
heading, and then, on the Format tab, in the Columns group, click Insert Column.
A list of fields appears. -
Click Assignment
Units. -
Click the Start column
heading, and then, on the Format tab, in the Columns group, click Insert Column. -
Click Peak.
Project inserts the Assignment Units and Peak columns to the
left of the Start column. Peak is the resource’s maximum units
value at any time throughout the assignment’s duration.
You can see that task 8 has a total work value of 240 hours,
a resource assignment units value of 200%, and a duration of 15
days. Next, you will change the task’s duration to observe the
effects on the other values.
After a discussion between the two copyeditors about who
will perform the copy-edit, you all agree that the task’s duration
should increase and the resource’s daily work on the task should
decrease correspondingly. -
In the Duration field for
task 8, type or select 20d, and
press the Enter key.
Project changes the duration of task 8 to 20 days and
increases the work to 320 hours. Note that the change highlighting
applied to the Work and Duration values. You increased the
duration and wanted the total work to remain the same (it didn’t),
so you will use the Action button to adjust the results of the new
task duration. -
Point at task 8’s Duration field, and then click the
Action button.
Review the options on the list that appears.
Because task 8’s task type is fixed units (the
default task type), the Action’s default selection is to increase
work as the duration increases. However, you’d like to keep the
work value the same and decrease assignment units for the task’s
new duration. -
On the Actions list,
click Resources will work fewer hours per
day so that the task will take longer.
The assignment units value decreases to 150%, and the total
work on the task remains unchanged at 240 hours.
Next, you will change a task type and then adjust the work
on the task. -
In the Task Name column,
select the name of task 24, Final
review. -
On the Task tab, in the
Editing group, click Scroll to Task.
Project displays work values for task 24, Final
review in the timephased grid. -
On the Task tab, in the
Properties group, click
Information.
The Task Information dialog box appears. -
Click the Advanced
tab.
The selected task describes the final review of the new
book’s page proofs. As you can see in the Task Type box, this task
has the default task type of fixed-units. The task is scheduled
for five days. You will make this a fixed-duration task. -
In the Task
Type box, select Fixed Duration. -
Click OK to close the
Task Information dialog
box.
Next, you’ll add work to the task. -
In the Work field for
task 24, Final review, type 150h, and then press Enter.
Because this is a fixed-duration task and you’ve
added work, Project adjusted the peak value to 125%; this
represents an intentional overallocation. On the right side of the
usage view, you can see that the resources assigned to task 24 now
have 10 hours of work scheduled per day. Their original assignment
units values of 100% each remain unaffected, however.
Clean Up
Close the Advanced Tasks A file.
|